Project description

EPC contractor Siemens sub-contracted the piping detail engineering and plant 3D modelling for a 3 x 67.5 MW gas-fired power plant to its approved global vendor Citec.

Citec's scope

Citec delivered the piping system including entire steam water cycle with FW piping up to boiler and steam piping from boiler terminal, turbine auxiliary piping – oil and gland system, main and auxiliary CW piping, drain and vent system, HP bypass system.

 

Case in brief
Customer: Siemens
Project location: India
Year completed: 2013
Technical data:

Applicable Code / Standards and References:
ASME B31.1.2010
IBR Regulation 2011
EJMA Ninth edition
Associated ANSI / ASTM standards